Contract flexibility is key to addressing a customer’s pricing, progress expectations
Pricing construction goods and services during the pandemic has become a roll of the dice.
Early manufacturing lockdowns and a downturn in the economy caused labor pools to shrink and material production to slow. As construction recovered from the initial shock, demand began to outstrip supply, causing prices to soar. This phenomenon triggered breakdowns in several key sectors, including manufacturing, labor and transportation.
Inevitably, supply chain issues lead to price escalation and delays. When goods and services are more difficult to obtain, prices increase and delivery schedules are unreliable. Since October 2020, steel prices have increased by more than 140 percent, gypsum products rose nearly 25 percent and insulation jumped by 17 percent. In the transportation sector, trucking costs are up 16 percent, and fuel costs have nearly doubled. Scheduling issues are also becoming the norm.
A local client recently shared that the wait for cabinets is 16 to 20 weeks, for high-end kitchen and laundry appliances it is six to eight months, and for most furnishings, it’s a minimum of nine months.
Although the basic concepts of price escalation and schedule slippage are not new to owners or contractors, the confluence of supply chain issues and market volatility in the wake of Covid-19 have made it extremely difficult to guarantee firm completion dates or deliver projects under traditional fixed price models.
Contractors are faced with the choice of building escalation risks into fixed pricing and potentially overbidding, or using current pricing and footing the bill for all post-contract increases. The choice can be equally vexing to owners who overpay in one scenario and face significant cost overruns in the other.
A cautious detente
The construction industry has addressed this dilemma by incorporating “price escalation clauses” into commercial and residential contracts.
A typical clause entitles the contractor to a post-contract price adjustment when certain predetermined market conditions occur, resulting in significant increases in its cost of labor, equipment, materials or services. The clause may compensate the contractor for every dollar of the escalation, resulting in the lowest bid value to the owner, or only for escalations reaching a certain minimum threshold, requiring the owner and the contractor to share the risk. Escalation compensation may also be subject to caps or percentage limits.
A well-written clause will
identify the covered categories of goods and services, a benchmark by
which the escalation will be measured, any applicable threshold or cap,
the mark-up for overhead and profit to be applied (if any), and how the
request will be documented and supported by the contractor.
After
more than two years of dealing with supply chain issues, I do believe
that owners and contractors appear to be settling into a cautious
detente. Owners are learning that escalation clauses can bring initial
pricing down, and that controls can be written into these clauses to
avoid uncontrolled exposure. Contractors are realizing that they can use
escalation clauses to deliver competitive pricing in a very volatile
market. As a result, if drafted thoughtfully, these clauses are not
likely to draw as much fire from either side.
Contractual path
Unfortunately,
the open-ended delays caused by supply chain issues can be far more
problematic than pricing issues. Originally, the industry turned to
force majeure (FM) clauses for protection. FM clauses generally require
the owner to excuse and grant schedule extensions for delays caused by
circumstances that are beyond the contractor’s control.
In
traditional form, however, FM clauses require the conditions causing
the delay to be unforeseeable and provide no compensation for the delays
to either side, regardless of how long they continue. Moreover, FM
clauses are often unclear on whether the contractor can demobilize
during the delay to pursue other work, or whether it must “stand by” and
attempt to make progress where possible.
The
alternative to FM clauses is somewhat counter-intuitive, because it
resorts to the suspension and termination provisions of the contract.
The
risk of damages flowing from a termination is difficult to justify
unless victory is clear. However, there are times when both parties
would be best served by an escape clause that allows them to negotiate a
proper end to, or hiatus from, the project as originally envisioned.
This is particularly true when supply chain issues create a “cardinal
change” in the nature of the work, or a substantial deviation in
contract obligations so profound that it changes the nature of the
bargain. Excessive schedule delays can rise to this level.
Furthermore,
although many standard contract forms do allow termination by the
contractor under dire circumstances, these provisions usually require a
government-imposed order to stop all project work. This rarely occurs
and leaves the contractor subject to many scenarios where it must
continue despite extremely unfavorable circumstances.
On
the flip side, although the owner typically has the right to terminate
“for convenience,” allowing it to walk away from the project for any
reason or no reason at all, a hefty termination fee often applies to
this decision. That result may not be fair where supply chain issues are
responsible for the delay.
In
light of these considerations, it makes sense to consider giving owners
and contractors a contractual path to end or postpone the project where
supply chain issues are likely to inflict undue hardship. This can be
accomplished by adding or modifying suspension and termination
provisions. A well-drafted clause should narrowly define the
circumstances under which a supply chain impact justifies suspension or
termination, and how each party will be protected without creating
unwarranted financial windfalls or pitfalls for either side. This saves
the parties from a Hobson’s choice between continuing forward during a
costly and indefinite delay, or pulling the trigger on typical
termination clauses which are designed for a default scenario and often
lead to punitive results.
In
short, triumphing over supply chain issues requires a creative contract
negotiation process. Heavy-handed penalty clauses and draconian pricing
policies simply do not work. The goal is to leave both sides with some
flexibility to decide their own fate when supply chain issues confound
pricing and progress expectations. This motivates the parties to resolve
supply issues fairly and preserve their mutual interest in completing
the project, without risking financial ruin.
Attorney Kelly Gagliuso is a construction litigator and shareholder based in the Manchester office of Bernstein Shur.
The confluence of supply chain issues and market
volatility in the wake of Covid-19 have made it difficult to guarantee
firm completion dates or deliver projects under traditional fixed price
models.